Forecasting Right-of-Way (ROW) acquisition timeline of transportation projects

Shiqin Zeng (School of Civil and Environmental Engineering, Georgia Institute of Technology, Atlanta, Georgia, USA)
Frederick Chung (School of Civil and Environmental Engineering, Georgia Institute of Technology, Atlanta, Georgia, USA)
Baabak Ashuri (School of Building Construction, School of Civil and Environmental Engineering, Georgia Institute of Technology, Atlanta, Georgia, USA)

Built Environment Project and Asset Management

ISSN: 2044-124X

Article publication date: 28 November 2023

Issue publication date: 14 March 2024

48

Abstract

Purpose

Completing Right-of-Way (ROW) acquisition process on schedule is critical to avoid delays and cost overruns on transportation projects. However, transportation agencies face challenges in accurately forecasting ROW acquisition timelines in the early stage of projects due to complex nature of acquisition process and limited design information. There is a need of improving accuracy of estimating ROW acquisition duration during the early phase of project development and quantitatively identifying risk factors affecting the duration.

Design/methodology/approach

The quantitative research methodology used to develop the forecasting model includes an ensemble algorithm based on decision tree and adaptive boosting techniques. A dataset of Georgia Department of Transportation projects held from 2010 to 2019 is utilized to demonstrate building the forecasting model. Furthermore, sensitivity analysis is performed to identify critical drivers of ROW acquisition durations.

Findings

The forecasting model developed in this research achieves a high accuracy to predict ROW durations by explaining 74% of the variance in ROW acquisition durations using project features, which is outperforming single regression tree, multiple linear regression and support vector machine. Moreover, number of parcels, average cost estimation per parcel, length of projects, number of condemnations, number of relocations and type of work are found to be influential factors as drivers of ROW acquisition duration.

Originality/value

This research contributes to the state of knowledge in estimating ROW acquisition timeline through (1) developing a novel machine learning model to accurately estimate ROW acquisition timelines, and (2) identifying drivers (i.e. risk factors) of ROW acquisition durations. The findings of this research will provide transportation agencies with insights on how to improve practices in scheduling ROW acquisition process.

Keywords

Citation

Zeng, S., Chung, F. and Ashuri, B. (2024), "Forecasting Right-of-Way (ROW) acquisition timeline of transportation projects", Built Environment Project and Asset Management, Vol. 14 No. 2, pp. 129-146. https://doi.org/10.1108/BEPAM-02-2023-0039