The Last-Planner-System’s impact on project culture

Gunnar Jürgen Lühr (Department of Project Management, Alma Mater Europaea – Evropski Center Maribor, Maribor, Slovenia)
Marian Bosch-Rekveldt (TU Delft, Delft, The The Netherlands)
Mladen Radujković (Department of Project Management, Alma Mater Europaea – Evropski Center Maribor, Maribor, Slovenia)

Journal of Engineering, Design and Technology

ISSN: 1726-0531

Article publication date: 7 September 2021

Issue publication date: 8 November 2023

269

Abstract

Purpose

The purpose of this paper is to investigate the Last-Planner-System’s impact on project cultures in terms of partnering.

Design/methodology/approach

A case study was performed using multiple data gathering approaches. The project cultures of three projects not applying the Last-Planner-System were compared with three projects that apply the Last-Planner-System. In total, 30 participants were involved in the study. Semi-structured interviews were held and analysed by applying qualitative content analysis. Also, the “organizational culture assessment instrument”, which belongs to the “competing values framework”, was used by means of an online survey.

Findings

The Last-Planner-System leads to increased levels of mutual understanding and control about the tasks and issues of the other parties. This detailed overview leads towards a more distinguished evaluation of the trustworthiness of individuals. This does not necessarily lead to a partnering project culture.

Originality/value

The contribution to research is that higher levels of transparency and mutual understanding do not necessarily lead to a high level of trust. Rather, transparency could be seen as a controlling mechanism that leads to better-founded estimations about the trustworthiness of others in the project.

Keywords

Citation

Lühr, G.J., Bosch-Rekveldt, M. and Radujković, M. (2023), "The Last-Planner-System’s impact on project culture", Journal of Engineering, Design and Technology, Vol. 21 No. 5, pp. 1303-1322. https://doi.org/10.1108/JEDT-05-2021-0285