To read this content please select one of the options below:

Corrosion Problems and the SHELLHAVEN‐ROMFORD PIPELINE

Anti-Corrosion Methods and Materials

ISSN: 0003-5599

Article publication date: 1 March 1958

12

Abstract

Between April and October 1957 the North Thames Gas Board constructed a 24‐in. pipeline between Shellhaven and Romford for the conveyance of oil refinery gas, the length of the line being 15½ miles. In recent years the Board has been trying out several new methods of gas‐making, including converting oil to gas by catalytic methods. The laying of the pipeline inaugurates the scheme to use refinery gases to turn into town's gas.

Citation

(1958), "Corrosion Problems and the SHELLHAVEN‐ROMFORD PIPELINE", Anti-Corrosion Methods and Materials, Vol. 5 No. 3, pp. 78-80. https://doi.org/10.1108/eb043912

Publisher

:

MCB UP Ltd

Copyright © 1958, MCB UP Limited