To read this content please select one of the options below:

Investigating ground-related design deficiencies as potential triggers to cost overruns in highway projects

Alolote Ibim Amadi (Department of Quantity Surveying, Rivers State University, Port Harcourt, Nigeria)

Journal of Financial Management of Property and Construction

ISSN: 1366-4387

Article publication date: 4 December 2023

21

Abstract

Purpose

This study aims to investigate ground-related design deficiencies as potential avenues of avoidable cost overruns, discernible from the geotechnical practices of highway agencies in the Niger Delta region of Nigeria.

Design/methodology/approach

The study deploys an interpretivist qualitative methodology to provide a detailed descriptive analysis of the design-related geotechnical practices of highway agencies during the pre-contract phase of highway projects. Semi-structured interviews were conducted with in-house professionals, consultants and contractors affiliated with the three highway agencies in the Niger Delta and thematically analysed to identify significant deviations from geotechnical best practices.

Findings

The study outcome shows that during the pre-contract phase, a chain of design-related geotechnical shortcomings has plagued highway projects executed in the Niger Delta. This view of practice uncovered in this study demonstrates a culture of significant deviation from best practice recommendations, which could plausibly contribute to the history of significant project cost overruns recorded in the region.

Originality/value

The study qualitatively spotlights gaps in the practice of highway agencies and reinforces the need for a re-orientation of the attitude to risk management, to give geotechnical concerns a priority in the financial management of highway projects executed in the Niger Delta region of Nigeria.

Keywords

Citation

Amadi, A.I. (2023), "Investigating ground-related design deficiencies as potential triggers to cost overruns in highway projects", Journal of Financial Management of Property and Construction, Vol. ahead-of-print No. ahead-of-print. https://doi.org/10.1108/JFMPC-02-2023-0008

Publisher

:

Emerald Publishing Limited

Copyright © 2023, Emerald Publishing Limited

Related articles